Change state in workorders

Moderator: crythias

Post Reply
patand
Znuny newbie
Posts: 4
Joined: 07 Oct 2010, 10:30
Znuny Version: 2.4.8

Change state in workorders

Post by patand »

Dear all,

I would like to manually change the state of a workorder within the change-management.

So far I figured out that manually changing the state of a workorder can be done in "Report".

My ITSM::ChangeManagement::WorkOrder::State: shows following states:
START
Created
Accepted
Ready
In Progress
Closed
Canceled

Within the "Report" of a workorder only following states are selectable:
Accepted
Ready
Canceled

I did not find any possibility to configure that all states are shown in the "Report" of a workorder

Is there a possibility to show all states in the "Report"?

Any help will be appreciated

Thanks

Andreas
Amukinado
Znuny newbie
Posts: 76
Joined: 02 Jun 2010, 15:52
Znuny Version: 3.2.8
Location: Portugal

Re: Change state in workorders

Post by Amukinado »

I'm with you on this one. Anyone kind enough to help, please?

Regards
OTRS V3.2.8 - ITSM 3.2.6 - Cent OS 5.9x64
jojo
Znuny guru
Posts: 15019
Joined: 26 Jan 2007, 14:50
Znuny Version: Git Master
Contact:

Re: Change state in workorders

Post by jojo »

Please read the OTRS::ITSM Admin Book. There is a detailled description of the Change Management Module and the State Machine used.
"Production": OTRS™ 8, OTRS™ 7, STORM powered by OTRS
"Testing": ((OTRS Community Edition)) and git Master

Never change Defaults.pm! :: Blog
Professional Services:: http://www.otrs.com :: enjoy@otrs.com
Post Reply