Is it possible to have multiple Transitions between Activities?
Say I have two Activities linked by Transition_1. The linking looks for a 'Yes' or 'No' in a drop-down as I want it to move on regardless of what is chosen. It just needs to move on to the next Activity and change the queue. This is fine and works. But I also want to have another Transition. Transition_2, which is dependent on a 'Yes' (only) from another drop down, which then creates a new ticket. Again, the Create Ticket Transition Action works fine If I add it to Transition_1, but I obviously don't want to create the new ticket every time. Only when a 'Yes' is selected in that drop-down.
Tldr:
On the same Activity:
Drop-down 1: Yes or No
Drop-down 2: Yes
Ticket moves on and the new Ticket is created.
Drop-down 1: Yes or No
Drop-down 2: No
Ticket moves on and the new Ticket is NOT created.
I can't get it to create the new ticket in this scenario.
Hope you can help.
---------------------------------------------------
This is using OTRS v 5.0.5 on Linux, Debian.
Multiple Transitions between Activities
Moderator: crythias
-
- Znuny newbie
- Posts: 38
- Joined: 15 Mar 2015, 10:31
- Znuny Version: v4.0.5 (Debian)
-
- Moderator
- Posts: 10170
- Joined: 04 May 2010, 18:38
- Znuny Version: 5.0.x
- Location: SouthWest Florida, USA
- Contact:
Re: Multiple Transitions between Activities
OTRS 6.0.x (private/testing/public) on Linux with MySQL database.
Please edit your signature to include your OTRS version, Operating System, and database type.
Click Subscribe Topic below to get notifications. Consider amending your topic title to include [SOLVED] if it is so.
Need help? Before you ask
Please edit your signature to include your OTRS version, Operating System, and database type.
Click Subscribe Topic below to get notifications. Consider amending your topic title to include [SOLVED] if it is so.
Need help? Before you ask
-
- Znuny newbie
- Posts: 38
- Joined: 15 Mar 2015, 10:31
- Znuny Version: v4.0.5 (Debian)
Re: Multiple Transitions between Activities
It just doesn't create the new ticket. It moves the Process on and performs all Transition Actions that are assigned to the first Transition, but seems to ignore my other Transition Action assigned to my second Transition.
Thanks for the link. I will check that out.
Thanks for the link. I will check that out.
Last edited by JeremyB3ntham on 15 Jan 2016, 18:49, edited 1 time in total.
-
- Moderator
- Posts: 10170
- Joined: 04 May 2010, 18:38
- Znuny Version: 5.0.x
- Location: SouthWest Florida, USA
- Contact:
Re: Multiple Transitions between Activities
Note that Transitions are criteria, and Transition Actions are what happens if criteria is matched (besides then going to the next Activity).
OTRS 6.0.x (private/testing/public) on Linux with MySQL database.
Please edit your signature to include your OTRS version, Operating System, and database type.
Click Subscribe Topic below to get notifications. Consider amending your topic title to include [SOLVED] if it is so.
Need help? Before you ask
Please edit your signature to include your OTRS version, Operating System, and database type.
Click Subscribe Topic below to get notifications. Consider amending your topic title to include [SOLVED] if it is so.
Need help? Before you ask
-
- Znuny newbie
- Posts: 38
- Joined: 15 Mar 2015, 10:31
- Znuny Version: v4.0.5 (Debian)
Re: Multiple Transitions between Activities
Yeah, sorry. I know that just wrote it wrong. Have edited my post.crythias wrote:Note that Transitions are criteria, and Transition Actions are what happens if criteria is matched (besides then going to the next Activity).