Changing creation date help

Moderator: crythias

Locked
freddiequah
Znuny newbie
Posts: 2
Joined: 23 Jul 2012, 08:47
Znuny Version: 3.1.7

Changing creation date help

Post by freddiequah »

Is there a way to edit the creation date?

The reason is I want the creation date to be the date when an incident is reported. From there I can know the actual timing from the incident get reported to resolve.

At the moment, the report is not very accurate as it is showing only from date the ticket is created to date the ticket resolved.
jojo
Znuny guru
Posts: 15020
Joined: 26 Jan 2007, 14:50
Znuny Version: Git Master
Contact:

Re: Changing creation date help

Post by jojo »

No you can not...


Typically the ticket should be created at the moment the incident is reported
"Production": OTRS™ 8, OTRS™ 7, STORM powered by OTRS
"Testing": ((OTRS Community Edition)) and git Master

Never change Defaults.pm! :: Blog
Professional Services:: http://www.otrs.com :: enjoy@otrs.com
freddiequah
Znuny newbie
Posts: 2
Joined: 23 Jul 2012, 08:47
Znuny Version: 3.1.7

Re: Changing creation date help

Post by freddiequah »

jojo wrote:No you can not...


Typically the ticket should be created at the moment the incident is reported

Thanks for the confirmation. I have created a Dynamic field called "Reported Date", and wondering if it is possible to calculate the SLA time based on reported time with SLA escalation time?
jojo
Znuny guru
Posts: 15020
Joined: 26 Jan 2007, 14:50
Znuny Version: Git Master
Contact:

Re: Changing creation date help

Post by jojo »

no, SLAs cn not calculated on dynamic fields
"Production": OTRS™ 8, OTRS™ 7, STORM powered by OTRS
"Testing": ((OTRS Community Edition)) and git Master

Never change Defaults.pm! :: Blog
Professional Services:: http://www.otrs.com :: enjoy@otrs.com
Locked